On the eve of the new year, 2021, workers of the construction and installation department for gasification of the Mary region of the «Turkmengazupjunchilik» association completed work to provide the population of the Vatan daikhan association with natural gas.
A gas pipeline with a total length of 10,468 meters was laid there. The main source of gas supply to the high-pressure ring gas pipeline is the Shatlyk gas distribution station.
Along with metal pipes in the construction of gas pipelines, reliable and high quality polyethylene pipes with a diameter of 225 and 315 mm of domestic production were used.
Since the beginning of 2020, gas workers have also regularly performed technical inspections, maintenance of gas equipment and overhaul of gas pipelines and gas systems on the territory of Mary region.
The professional fulfillment by gas workers of the tasks assigned to them to ensure uninterrupted supply of consumers with natural gas and the safe operation of gas supply systems is one of the important components of the overall contribution to the socio-economic development of the region and improving the quality of life of the population.